Q35. Holly is the project manager of the NHQ project for her company. Her project sponsor, Tracy, has requested that Thomas, the department manager, from the Risk Management Department, will work with Holly to determine the effectiveness of the risk responses. Tracy and Thomas are concerned that some of the risks within Holly’s project may not be addressed to depth they would like. In this scenario, who is responsible for ensuring that risk audits are performed at an appropriate frequency throughout the project?

 
 
 
 

Q36. During the weekly project meeting a risk manager identified new risks in the last sprint, which might impact the project cost by implementing mitigation plans. The sponsor and some project team members do not agree that those risks can impact the project cost.
What should the risk manager do to resolve the sponsor and project team members’ concerns about risk identification?

 
 
 
 

Q37.

The project values are in thousands. The project manager has a budget of US$8,000,000 for this project and asks how much more would be needed to add to the contingency reserve for a P40?

 
 
 
 

Q38. Upon reviewing the risk analysis results, the project manager notices several risks that occur more frequently than others. What should the project manager do?

 
 
 
 

Q39. After years of experience, a project manager becomes the lead manager for a company. This new lead manager asks all project managers to use a specific technique when they perform qualitative risk analysis on their projects. This technique consists of achieving the relative weighting of the project’s objectives in terms of priority to the stakeholders.
What is the name of this technique?

 
 
 
 

Q40. You are the project manager of a large project that will last four years. In this project, you would like to model the risk based on its distribution, impact, and other factors. There are three modeling techniques that a project manager can use to include both event-oriented and project-oriented analysis. Which modeling technique does NOT provide event-oriented and project-oriented analysis for identified risks?

 
 
 
 

Q41. A risk manager for a hospital extension project is leading a project team in developing a risk management plan. One team member is responsible for conducting risk identification. The team member just joined the team and is struggling to ensure the coverage of all risks that might arise in this complex project.
How should the risk manager address this concern?

 
 
 
 

Q42. A project manager managing a high-risk rating project was just informed that one of the key project resources has decided to leave the organization. The project manager asks the risk manager for their recommendations.
The risk manager previously identified this as a risk and had created a transition plan to enable another resource to carry out the same duties. The risk manager was informed that by transitioning the responsibilities to the new resource, new risks to the completion dates of other project-related tasks appear.
What should the risk manager advise the project manager?

 
 
 
 

Q43. During a risk identification session, the risk manager notices that subject matter experts (SMEs) are reluctant to participate because some risks could expose the poor maturity of processes in other business units. Which risk analysis technique should the risk manager use?

 
 
 
 

Q44. After presenting a list of risks to the major project stakeholders and project sponsor, the board requested the risks be sorted differently from the results presented by the project team. This is a major issue and will cause a
2-week delay in the project.How could the risk manager have avoided the board’s response?

 
 
 
 

Q45. You work as a project manager for BlueWell Inc. Your project is using a new material to construct a large warehouse in your city. This new material is cheaper than traditional building materials, but it takes some time to learn how to use the material properly. You have communicated to the project stakeholders that you will be able to save costs by using the new material, but you will need a few extra weeks to complete training to use the materials. This risk response of learning how to use the new materials can also be known as what term?

 
 
 
 

Q46. The project team has correctly identified, assessed, and planned responses for a project’s risks. The risk manager is required to prepare a quarterly report on the performance of managing the risks.
What are two options the risk manager should consult for the analysis? (Choose two.)

 
 
 
 
 

Q47. A risk manager reviews a Monte Carlo schedule risk analysis model before sharing the results with the project manager. The risk manager notices that activity correlations were not included in the model.
What is an effect of adding the correlation to the model?

 
 
 
 

Q48. During a brainstorming session, a stakeholder identifies a risk that, if realized, could greatly impact their team. The stakeholder insists that this particular risk should be mitigated to the greatest extent possible, however, the majority of other stakeholders feel that different risks have higher probabilities of occurring.
Which action should the risk manager take to address this risk?

 
 
 
 

Q49. The company is a risk seeking organization, and has experienced measurable success based on their current strategy for growth. A new project has an overall project risk that exceeds the risk levels documented in the risk management plan.
What would be the best course of action for the company to take with the project based on its current scope?

 
 
 
 

Q50. You are the project manager of the GHY Project for your company. You need to complete a project management process that will be on the lookout for new risks, changing risks, and risks that are now outdated. Which project management process is responsible for these actions?

 
 
 
 

Ace PMI PMI-RMP Certification with Actual Questions Jan 31, 2026 Updated: https://www.examcollectionpass.com/PMI/PMI-RMP-practice-exam-dumps.html

         

Related Links: myportal.utt.edu.tt scalar.usc.edu learn.csisafety.com.au knowyourmeme.com www.slideshare.net myportal.utt.edu.tt

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below